Sr. No. Name of Work Name of Executing Agency/ Deptt. Estimated Cost/ Total Cost Funds Released  Exp.           Remarks
1 Const. of Irrigation Kuhal & Tank in village Marog, Bachro, Samral, Bidhna, Rewari, Kharta, johdi & Ghabag, GP Bhoj Naita BDPO, Morni 12.00 42.00 9.00 Work in progress
2 Const. of Irrigation Kool & Irrigation Tank  with R/wall in village Kathi G.P. Bhoj Koti. 15.00 5.00 Work in progress
3 Const.of (350 mtr) Irrigation Kool in village Mandi, G.P. Bhoj Jabyal 15.00 6.00 Work in progress
  Sub-Total    42.00 42.00 20.00  
4 Installation of 14 nos. Handpumps in village Baas Chela, Kangar, damesha, Chakoh, Mau, Dera Johri, Nala Ghat, Karechi Mod, Khoi, Dakrog, Paploh, Kainan, Dhaman & sanoi in Block Morni & Pinjore. XEN, PH, Panchkula 45.91 30.00 20.78 6 Nos. of handpumps installed & commissioned,work in progress 
  Sub-Total    45.91 30.00 20.78  
5 Const. of Rasta from Kanderan to Bela Block Morni range  DFO, Morni at Pinjore 51.43 51.43 0.00 tender process is going on 
  Sub-Total    51.43 51.43 0.00  
6 Const. of Irrigation Kool in village Mangniwala block Pinjore BDPO, Pinjore 12.00 35.00 7.98 Work in progress
7 Const. of Irrigation Kool from Hanuman Mandir to Field of Sh. Soundi Ram & field of Sh. Lajja Ram in village Janouli 15.00 8.96 Work in progress
8 Const. of Irrigation Kool from main Irrigation Kool to field of Sh. Lekh Raj & from Road to field of Sh. Rajkumar in village Toran 8.00 5.62 Work in progress
  Sub-Total    35.00 35.00 22.56  
9 Const. of Retaining wall of Naiyawala Johar in Village Barwala BDPO, Barwala 8.00 30.00 0.30 Work in progress
10 Const. of Nala from Hada-Rodhi to Bator puli in Village Barwala 5.00 3.89 work completed 
11 Construction of Hall near Shiv Mandir in Village Rattewali  8.00 8.00 work completed 
12 Const. of SC Dharamshala in Village Khetpurali 9.00 9.00 work completed 
  Sub-Total    30.00 30.00 21.19  
13 Const. of Irrigation Kool from h/o Sh. Data Ram to h/o Rishi Pal in village Bharouli Block Barwala BDPO, Barwala 8.00 8.00 6.00 Work in progress
  Sub-Total    8.00 8.00 6.00  
14 Const. of Danga nera house of Sh. Gurdev Singh & const. of danga for street in village Godam GP Thane ki Sair Block Pinjore BDPO, Pinjore 17.50 10.00 9.76 Work in progress
  Sub-Total    17.50 10.00 9.76  
15 Const. of Irrigation Kool from field of Sh. Sumer to field of Sh. Chaman Lal in village Bakshiwala Block Pinjore BDPO, Pinjore  10.00 45.00 2.23 work in progress
16 Const. of Irrigation Kool from main kool to farm house Sh. Sohana lal in village Bar Block Pinjore 7.00 1.64 work in progress
17 Const. of Tank and lying of pipe from Tubewell of Sh. Mohan Singh to Harijan Basti, Tubewell of Sh. Nihal Singh to farm of Sh. Singhara Singh and Tubewell of Sh. Chanan Singh to farm of Sh. Somnath Singh in village Karanpur Block Pinjore 6.00 2.80 work in progress
18 Const.of Irrigation Kool from village Ambwala Tubewell to back side of School in village Kotia Block Pinjore 9.00 4.80 work in progress
19 Const. of Irrigation Kool from field of Sh. Pyare to hous of Sh. Sardara on village Kharkhua Block Pinjore 15.00 0.00 work not started
20 Const. of Irrigation Kool from field of Sh. Amar Singh to Pond in village Nala Balog GP Jabrot  4.00 0.99 work in progress
21 Const. of Irrigation Kool from field of Sh. Satnam to Sh. Kultar in village Chicken. 15.00 4.34 work in progress
  Sub-Total    66.00 45.00 16.80  
22 Const.of 10 nos. CSMS. R/wall in village Gawahi/ Dakrog Block Pinjore  ASCO, Panchkula 24.00 71.00 23.89 work completed 
23 Const. of 2 nos. Sub Surface Dam & Irrigation Tank in Village Khoi Block Pinjore  9.00 9.00 work completed 
24 Const. of Irrigation Kuhal in village Dhamsu Block Pinjore  8.00 8.00 work completed 
25 Const. of 2 nos Irrigation Tank in village Jabrot Block Pinjore  6.00 6.00 work completed 
26 Const. of 5 nos. SDD/EGP in Village Bir Firojari Block Barwala  14.00 14.02 work completed 
27 Const. of 4 nos. SDD/EGP in village Billah Block Barwala  10.00 10.00 work completed 
  Sub-Total    71.00 71.00 70.91  
28 Const. of Irrigation Kool (400 mtr.) in village Bhoj Rajpura Block Morni ASCO, Raipurrani 18.00 57.00 17.97 work completed 
29 Const. of 6 nos CMS in village Garhi Kotaha Block Raipurrani 11.00 11.00 work completed 
30 Const. of Drop Structure & Retaining wall in village Garhi Kotaha Block Raipurrani (scheme changed vide this office letter No. SDA-2019/495 dt. 08-03-19 in lieu of Const. of 3 nos SDD/EGP)   10.00 8.85 Work in progress
31 Const. of Create wire structure, water Tank, Lying of Pipeline and R/Wall in village Gwahi, Chalan Theli, Thatha in GP Thandog Block Raipurrani 18.00 15.94 Work in progress
  Sub-Total    57.00 57.00 53.76  
32 Const. of Irrigation Kool in village Mandapa Block Raipurrani BDPO, Raipurrani 8.00 8.00 0.00 non availability of cement w.e.f. 1/03/19
  Sub-Total    8.00 8.00 0.00  
33 Disliting of Kool and Laying of Pipeline in village Mandapa BDPO, Raipurrani 18.00 10.00 0.00 non availability of cement w.e.f. 1/03/19
  Sub-Total    18.00 10.00 0.00  
  Total    449.84 397.43 241.76