District Ambala | (Rs. in lacs) | |||||
Sr. No. | Name of Work/ Schemes | Name of Executing Agency/ Deptt. | Estimated Cost/Total Cost | Funds Released | Exp. | Remarks |
1 | P/F of LED street light fitting Farhi Market in Dina Ki Mandi, Sardar Zone | Commissioner, Municipal Corporation, Ambala Cantt | 13.33 | 70.00 | 10.42 | Work completed, Balance refunded |
2 | Const. Of Road & Boundry wall from Dina Ki Mandi Park to Sushil Polish Shop in Valmiki Basti in Rambagh Road in ward No. 17 | 27.24 | 27.24 | |||
3 | Installation of street light line with LED light fitting in Nanhera Village from NH-I to Cross Road, Ward No. 20, Ambala Sadar | 31.11 | 25.06 | |||
Sub-Total | 71.68 | 70.00 | 62.72 | |||
4 | Development of Vacant Land rehri & Farri site at dina mandi Ward no. 19 (Ambala Cantt.) | Commissioner, Municipal Corporation, Ambala Cantt. | 43.00 | 43.00 | 42.90 | Work completed, Balance refunded |
Sub-Total | 43.00 | 43.00 | 42.90 | |||
5 | Construction of Community Centre in Village Kakru | Commissioner, Municipal Corporation, Ambala City | 25.00 | 50.00 | 24.69 | Work completed, Balance refunded |
6 | Construction of Community Centre in Village Saddopur | 25.00 | 24.06 | |||
Sub-Total | 50.00 | 50.00 | 48.75 | |||
7 | Installation of Tubewell at Yamkeshwar Tirath Sthal Hussiani Block Naraingarh | XEN, Public Health Engineering Division, Naraingarh | 20.00 | 39.54 | 13.48 | Work completed, Balance refunded |
8 | Providing & Installation 1 No. Additional Tubwell in village Naugawan Block Naraingarh | 19.54 | 13.53 | Work completed, Balance refunded | ||
Sub-Total | 39.54 | 39.54 | 27.01 | |||
9 | Installation of Tubewell in village Shahpur Nurd Block Naraingarh | XEN, Public Health Engineering Division, Naraingarh | 12.00 | 60.00 | 11.57 | Work completed, Balance refunded |
10 | Installation of Tubewell in village Bhuda Khera Block Naraingarh | 12.00 | 9.06 | |||
11 | Installation of Tubewell in village Badhouli Block Naraingarh | 12.00 | 11.29 | |||
12 | Installation of Tubewell in village Ganeshpur Block Naraingarh | 12.00 | 10.69 | |||
13 | Installation of Tubewell in village Khuda Khurd Block Shahzadpur (Place of Scheme changed as from Village Shahzadpur to Khuda Khurd) | 12.00 | 10.58 | |||
Sub-Total | 60.00 | 60.00 | 53.19 | |||
14 | WHS/Culvert with interception bundh cum Diversion embankment in village Khuda Block Ambala-I | ASCO, Naraingarh | 24.00 | 49.00 | 23.98 | Work completed, Balance refunded |
15 | Pond/Tank & Earth Work & Creat wire Spur in village Nagouli Block Naraingarh | 15.00 | 14.90 | |||
16 | Interception bundh cum diversion Embankment in village Dhukheri Block Ambala I | 10.00 | 10.00 | |||
Sub-Total | 49.00 | 49.00 | 48.88 | |||
17 | 3 Nos. Drop Str. With earthen embankment (140 Ha. Area) in village Nagla Nanku Block Shehzadpur | ASCO, Naraingarh | 15.00 | 25.00 | 15.00 | Work completed |
18 | 2 Nos. Drop Str. with Earthen Embankment (120 Ha. Area) in village Behlouli Block Shahzadpur | 10.00 | 9.96 | Work completed, Balance refunded | ||
Sub-Total | 25.00 | 25.00 | 24.96 | |||
19 | Stone Masonry Cool in villages Firozpur, Kathe Majra, Mugal Majra & RCC Pipe water cool in village Kotla Firozpur for approximately 8500 Running Mtrs. in Block Naraingarh (Revised/change of scheme on 10-01-2018 with Rs. 333.39 lacs in place of Rs. 225.00 lacs) | DFO (T), Ambala | 333.39 | 333.39 | 333.39 | work completed |
Sub-Total | 333.39 | 333.39 | 333.39 | |||
20 | Stone Massonary Structure in village Jangu Marjra Block Naraingarh (Chechi Majra Beat) | DFO(T), Ambala | 1.90 | 159.84 | 159.84 | Work completed |
21 | Construction of C.C. Stud in village Manglore Block Shehzadpur (Barri Bassi Beat) | 47.38 | ||||
22 | Construction of C.C. Stud in village Kurali Block Kurali (Kurali Beat) | 27.64 | ||||
23 | Construction of C.C. Stud in village Jangu Majra Block Shehzadpur (Barri Bassi Beat) | 35.54 | ||||
24 | Construction of C.C. Stud in village Hamidpur Block Naraingarh (Hamidpur Beat) | 47.38 | ||||
Sub-Total | 159.84 | 159.84 | 159.84 | |||
25 | Completion of phirni & construction of a culvert in village Dhurala Block Saha | XEN, PR, Ambala | 19.00 | 19.00 | 19.00 | Work Completed |
Sub-Total | 19.00 | 19.00 | 19.00 | |||
26 | Community Centre in village Kathgarh Block Ambala-I | XEN, PR, Ambala | 25.00 | 50.00 | 15.50 | Work in Progress, near completion |
27 | Community Centre in village Khurchanpur Block Ambala-I | 25.00 | 22.84 | work completed | ||
Sub-Total | 50.00 | 50.00 | 38.34 | |||
28 | Construction of shed of Cattle Crushes in the Govt. Vety. Hospitals(GVH), Majri, Jalbera, Sonda,Gaushala, Ambala City, Saha, Thakurpura, Samleheri, Dheen, Ballana, Ambala City, Naneola, Santokhi, Lakhnoura, Mukandpur, Sherpur District Ambala Construction of shed of Cattle Crushes in Govt. Vety. Dispensary, Tharwa, Bara, Bhanokheri, Kaula, Rupa-Majra, Machonda, Dukheri, Rampur-Chappra, Gola, Dhanoura, Salehpur,Kambassi, Gadholi, Banoundi, Kakkar Majra, Patvi, Fatehgarh, Dhanana,Raiwali,Jatwar, Naggal Gharoli, Korwa Khurd, Bharog,Racheri, Patrehri District Ambala Total 40 Nos. Sheds for above Cattle Crushes @ 59,000/- each =40x59000=23,60,000/- |
XEN, PR, Ambala |
23.60 | 15.00 | 15.00 | out of 40 No. works 17 works completed, 12 works in Propgress & 11 not started |
Sub-Total | 23.60 | 15.00 | 15.00 | |||
29 | Installation of Tubewell in village Himmatpura Distt. Ambala | XEN, Public Health Eng. Div., Ambala Cantt. | 23.51 | 23.51 | 20.65 | Work completed & commissioned on 31-01-19 but laibilities to be cleared |
Sub-Total | 23.51 | 23.51 | 20.65 | |||
30 | Supply of 1 No. Panchkarma Table and Steamer for Govt. Ayurvedic Dispensaries (GAD), Saha, Babyal, Khaira, Naneola, Baragara, Topkhana,Binjalpur, Talheri Gujran, Korwa Khurad, Rajoli, Jeoli, Rasidpur, Lakhnaura, Saunta, Nurhad @ 1.12 each(15 No.) | District Ayurvedic Officer, Ambala | 16.80 | 19.04 | 0.00 | Request made to Director for processing e-tendering |
31 | Supply of 1 No.Panchkarma Table and Steamer for Primary Health Centre(PHC), Nohani , Panjokhra | 2.24 | 0.96 | One panchkarma table, one steamer and one medicine counter purchased | ||
Sub-Total | 19.04 | 19.04 | 0.96 | |||
32 | Construction of 1 Km. Approch Road (between Phule Majara and Tepla Villages ) to KVK (Krishi Vigyan Kendra) | BDPO, Saha | 20.00 | 20.00 | 19.89 | Work completed, Balance refunded |
Sub-Total | 20.00 | 20.00 | 19.89 | |||
33 | District Ambala Supply of 40 Nos. of Cattle Crushes in the Govt. Vety. Hospitals(GVH), Majri, Jalbera, Sonda,Gaushala, Ambala City, Saha, Thakurpura, Samleheri, Dheen, Ballana, Ambala City, Naneola, Santokhi, Lakhnoura, Mukandpur, Sherpur Supply of Cattle Crushes in the Govt. Vety. Dispensary, Tharwa, Bara, Bhanokheri, Kaula, Rupa-Majra, Machonda, Dukheri, Rampur-Chappra, Gola, Dhanoura, Salehpur,Kambassi, Gadholi, Banoundi, Kakkar Majra, Patvi, Fatehgarh, Dhanana,Raiwali,Jatwar, Naggal Gharoli, Korwa Khurd, Bharog,Racheri, Patrehri (40 Nos. of Cattle Crush @ Rs. 17961/-) |
DGM, Haryana Agro Industries Corporation Ltd. Panchkula | 7.19 | 7.19 | 0.00 | Rates revised & department are requested to refund excess amount of cattle crush |
Total | 993.79 | 983.51 | 915.48 |